Wind Turbine Payback in Baker County, GA

Wind turbine payback in Baker County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Baker County, GA averages 4.66 m/s (10.4 mph). A 10 kW turbine there would make about 10,320 kWh a year, worth $1,597 at GA's 15.48¢/kWh. Against an installed cost of about $100,000, that is a payback of 63 years, and the turbine is built to last about 20.

What to do in Baker County

A home turbine is not worth buying for savings in Baker County unless your spot is far windier than the county average, 7.8 m/s at the hub against 4.66 m/s here. Per kW, solar panels would make about 1,396 kWh a year here against the turbine's 1,032, so get a solar quote first.

What would have to change

Against the rest of GA

Baker County is the 1,645th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in GA is Glynn County at 5.08 m/s, payback 49 years.

Month by month in Baker County

March is the strongest month here, at 5.29 m/s and about 1,235 kWh. July is the weakest, 3.63 m/s and 411 kWh, so the best month makes 3.0 times the worst. November to March brings in 54% of the year's output in Baker County.

MonthWind at 30 mOutputWorth
January5.23 m/s1,199 kWh$186
February5.25 m/s1,092 kWh$169
March5.29 m/s1,235 kWh$191
April5.04 m/s1,051 kWh$163
May4.45 m/s765 kWh$118
June3.84 m/s475 kWh$74
July3.63 m/s411 kWh$64
August3.68 m/s431 kWh$67
September4.52 m/s779 kWh$121
October4.82 m/s963 kWh$149
November5.11 m/s1,090 kWh$169
December5.13 m/s1,142 kWh$177

What a taller tower would buy

Measured at 10 m the wind in Baker County averages 3.47 m/s; at 50 m it is 5.35 m/s. That gives a shear exponent of 0.269, typical of ordinary open country. Going from 20 m to 50 m takes output from 7,522 to 14,963 kWh a year, 99% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m4.18 m/s7,522 kWh86 years
30 m4.66 m/s10,339 kWh63 years
40 m5.04 m/s12,794 kWh51 years
50 m5.35 m/s14,963 kWh43 years

Counties around Baker County

None of the 6 closest counties is windier than Baker County.

Sun versus wind in Baker County

Baker County gets 4.78 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,396 kWh a year; one kW of the turbine above makes 1,032. Kilowatt for kilowatt, panels make 1.4 times as much here as the turbine. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.