No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Cimarron County, OK averages 6.82 m/s (15.3 mph). A 10 kW turbine there would make about 25,747 kWh a year, worth $3,556 at OK's 13.81¢/kWh. Against an installed cost of about $100,000, that is a payback of 28 years, and the turbine is built to last about 20.

What to do in Cimarron County

A home turbine is not worth buying for savings in Cimarron County unless your spot is far windier than the county average, 8.4 m/s at the hub against 6.82 m/s here. Per kW, solar panels would make about 1,548 kWh a year here against the turbine's 2,575, so get a solar quote first.

What would have to change

Against the rest of OK

Cimarron County is the 30th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. It is the windiest county in OK.

Month by month in Cimarron County

April is the strongest month here, at 7.62 m/s and about 2,579 kWh. August is the weakest, 5.88 m/s and 1,597 kWh, so the best month makes 1.6 times the worst. November to March brings in 43% of the year's output in Cimarron County.

MonthWind at 30 mOutputWorth
January6.74 m/s2,136 kWh$295
February7.00 m/s2,073 kWh$286
March7.24 m/s2,441 kWh$337
April7.62 m/s2,579 kWh$356
May6.91 m/s2,241 kWh$309
June6.95 m/s2,195 kWh$303
July6.13 m/s1,754 kWh$242
August5.88 m/s1,597 kWh$221
September6.64 m/s2,008 kWh$277
October6.76 m/s2,153 kWh$297
November7.15 m/s2,310 kWh$319
December6.85 m/s2,208 kWh$305

What a taller tower would buy

Measured at 10 m the wind in Cimarron County averages 5.38 m/s; at 50 m it is 7.61 m/s. That gives a shear exponent of 0.215, typical of ordinary open country. Going from 20 m to 50 m takes output from 21,553 to 31,279 kWh a year, 45% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m6.25 m/s21,553 kWh34 years
30 m6.82 m/s25,736 kWh28 years
40 m7.25 m/s28,836 kWh25 years
50 m7.61 m/s31,279 kWh23 years

Counties around Cimarron County

None of the 6 closest counties is windier than Cimarron County.

Sun versus wind in Cimarron County

Cimarron County gets 5.3 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,548 kWh a year; one kW of the turbine above makes 2,575. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.7 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.