Wind Turbine Payback in Douglas County, OR

Wind turbine payback in Douglas County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Douglas County, OR averages 2.81 m/s (6.3 mph). A 10 kW turbine there would make about 2,073 kWh a year, worth $320 at OR's 15.46¢/kWh. Against an installed cost of about $100,000, that is a payback of over 100 years, and the turbine is built to last about 20.

What to do in Douglas County

A home turbine is not worth buying for savings in Douglas County unless your spot is far windier than the county average, 7.8 m/s at the hub against 2.81 m/s here. Per kW, solar panels would make about 1,183 kWh a year here against the turbine's 207, so get a solar quote first.

What would have to change

Against the rest of OR

Douglas County is the 3,122nd windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in OR is Gilliam County at 5.48 m/s, payback 41 years.

Month by month in Douglas County

December is the strongest month here, at 3.47 m/s and about 359 kWh. August is the weakest, 2.39 m/s and 96 kWh, so the best month makes 3.7 times the worst. November to March brings in 63% of the year's output in Douglas County.

MonthWind at 30 mOutputWorth
January3.37 m/s325 kWh$50
February3.01 m/s202 kWh$31
March2.99 m/s219 kWh$34
April2.67 m/s141 kWh$22
May2.40 m/s98 kWh$15
June2.41 m/s96 kWh$15
July2.39 m/s96 kWh$15
August2.39 m/s96 kWh$15
September2.53 m/s116 kWh$18
October2.83 m/s181 kWh$28
November3.23 m/s274 kWh$42
December3.47 m/s359 kWh$56

What a taller tower would buy

Measured at 10 m the wind in Douglas County averages 1.81 m/s; at 50 m it is 3.44 m/s. That gives a shear exponent of 0.399, typical of rough, sheltered ground: trees or buildings slow the low wind a lot. Going from 20 m to 50 m takes output from 1,128 to 4,094 kWh a year, 263% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m2.39 m/s1,128 kWhover 100 years
30 m2.81 m/s2,062 kWhover 100 years
40 m3.15 m/s3,057 kWhover 100 years
50 m3.44 m/s4,094 kWhover 100 years

Counties around Douglas County

5 of the 6 closest counties are windier at turbine height; the windiest, Curry County, averages 4.71 m/s.

Sun versus wind in Douglas County

Douglas County gets 4.05 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,183 kWh a year; one kW of the turbine above makes 207. Kilowatt for kilowatt, panels make 5.7 times as much here as the turbine. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.