Wind Turbine Payback in Guadalupe County, TX

Wind turbine payback in Guadalupe County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Guadalupe County, TX averages 5.35 m/s (12 mph). A 10 kW turbine there would make about 14,963 kWh a year, worth $2,399 at TX's 16.03¢/kWh. Against an installed cost of about $100,000, that is a payback of 42 years, and the turbine is built to last about 20.

What to do in Guadalupe County

A home turbine is not worth buying for savings in Guadalupe County unless your spot is far windier than the county average, 7.6 m/s at the hub against 5.35 m/s here. Per kW, solar panels would make about 1,402 kWh a year here against the turbine's 1,496, so get a solar quote first.

What would have to change

Against the rest of TX

Guadalupe County is the 1,303rd windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in TX is Dallam County at 6.82 m/s, payback 24 years.

Month by month in Guadalupe County

April is the strongest month here, at 6.00 m/s and about 1,617 kWh. September is the weakest, 4.54 m/s and 788 kWh, so the best month makes 2.1 times the worst. November to March brings in 48% of the year's output in Guadalupe County.

MonthWind at 30 mOutputWorth
January5.62 m/s1,438 kWh$231
February5.78 m/s1,388 kWh$222
March5.89 m/s1,604 kWh$257
April6.00 m/s1,617 kWh$259
May5.71 m/s1,493 kWh$239
June5.08 m/s1,076 kWh$172
July4.74 m/s917 kWh$147
August4.53 m/s810 kWh$130
September4.54 m/s788 kWh$126
October5.14 m/s1,148 kWh$184
November5.53 m/s1,338 kWh$214
December5.60 m/s1,421 kWh$228

What a taller tower would buy

Measured at 10 m the wind in Guadalupe County averages 4.13 m/s; at 50 m it is 6.03 m/s. That gives a shear exponent of 0.235, typical of ordinary open country. Going from 20 m to 50 m takes output from 11,615 to 19,926 kWh a year, 72% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m4.86 m/s11,615 kWh54 years
30 m5.35 m/s14,948 kWh42 years
40 m5.72 m/s17,653 kWh35 years
50 m6.03 m/s19,926 kWh31 years

Counties around Guadalupe County

6 of the 6 closest counties are windier at turbine height; the windiest, Comal County, averages 5.56 m/s.

Sun versus wind in Guadalupe County

Guadalupe County gets 4.8 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,402 kWh a year; one kW of the turbine above makes 1,496. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.1 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.