No. The turbine wears out before it pays for itself.
At 30 m, the height a home turbine tower usually reaches, the wind in Jackson County, MO averages 5.96 m/s (13.3 mph). A 10 kW turbine there would make about 19,408 kWh a year, worth $2,771 at MO's 14.28¢/kWh. Against an installed cost of about $100,000, that is a payback of 36 years, and the turbine is built to last about 20.
What to do in Jackson County
A home turbine is not worth buying for savings in Jackson County unless your spot is far windier than the county average, 8.2 m/s at the hub against 5.96 m/s here. Per kW, solar panels would make about 1,235 kWh a year here against the turbine's 1,941, so get a solar quote first.
What would have to change
- Power would have to cost 26¢/kWh, 1.8 times what MO pays now.
- Or the average wind at the hub would have to be 8.2 m/s instead of 5.96. A taller tower or an exposed ridge can add some of that; a rooftop never will.
Against the rest of MO
Jackson County is the 901st windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in MO is Atchison County at 6.17 m/s, payback 33 years.
Month by month in Jackson County
April is the strongest month here, at 6.92 m/s and about 2,177 kWh. August is the weakest, 4.68 m/s and 887 kWh, so the best month makes 2.5 times the worst. November to March brings in 49% of the year's output in Jackson County.
| Month | Wind at 30 m | Output | Worth |
|---|---|---|---|
| January | 6.38 m/s | 1,914 kWh | $273 |
| February | 6.36 m/s | 1,719 kWh | $245 |
| March | 6.70 m/s | 2,113 kWh | $302 |
| April | 6.92 m/s | 2,177 kWh | $311 |
| May | 6.01 m/s | 1,680 kWh | $240 |
| June | 5.58 m/s | 1,363 kWh | $195 |
| July | 4.72 m/s | 906 kWh | $129 |
| August | 4.68 m/s | 887 kWh | $127 |
| September | 5.35 m/s | 1,232 kWh | $176 |
| October | 6.22 m/s | 1,814 kWh | $259 |
| November | 6.52 m/s | 1,933 kWh | $276 |
| December | 6.23 m/s | 1,819 kWh | $260 |
What a taller tower would buy
Measured at 10 m the wind in Jackson County averages 4.6 m/s; at 50 m it is 6.73 m/s. That gives a shear exponent of 0.236, typical of ordinary open country. Going from 20 m to 50 m takes output from 15,471 to 25,093 kWh a year, 62% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.
| Hub height | Average wind | Output | Payback |
|---|---|---|---|
| 20 m | 5.42 m/s | 15,471 kWh | 45 years |
| 30 m | 5.97 m/s | 19,450 kWh | 36 years |
| 40 m | 6.38 m/s | 22,556 kWh | 31 years |
| 50 m | 6.73 m/s | 25,093 kWh | 28 years |
Counties around Jackson County
3 of the 6 closest counties are windier at turbine height; the windiest, Wyandotte County, averages 6.06 m/s.
- Clay County, MO: 5.99 m/s, 19,630 kWh, payback 36 years (22 mi)
- Wyandotte County, KS: 6.06 m/s, 20,149 kWh, payback 33 years (24 mi)
- Cass County, MO: 5.9 m/s, 18,964 kWh, payback 37 years (25 mi)
- Johnson County, KS: 6.06 m/s, 20,149 kWh, payback 33 years (27 mi)
- Ray County, MO: 5.89 m/s, 18,890 kWh, payback 37 years (28 mi)
- Lafayette County, MO: 5.86 m/s, 18,669 kWh, payback 38 years (29 mi)
Sun versus wind in Jackson County
Jackson County gets 4.23 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,235 kWh a year; one kW of the turbine above makes 1,941. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.6 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.
How this is worked out
Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.