TurbinePayback

Wind Turbine Payback in Madison County, IL

Wind turbine payback in Madison County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Madison County, IL averages 5.57 m/s (12.5 mph). A 10 kW turbine there would make about 16,544 kWh a year, worth $3,181 at IL's 19.23¢/kWh. Against an installed cost of about $100,000, that is a payback of 31 years, and the turbine is built to last about 20.

What to do in Madison County

A home turbine is not worth buying for savings in Madison County unless your spot is far windier than the county average, 6.8 m/s at the hub against 5.57 m/s here. Per kW, solar panels would make about 1,221 kWh a year here against the turbine's 1,654, so get a solar quote first.

What would have to change

Against the rest of IL

Madison County is the 1,180th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in IL is Cook County at 6.73 m/s, payback 21 years.

Month by month in Madison County

April is the strongest month here, at 6.54 m/s and about 1,948 kWh. July is the weakest, 4.17 m/s and 633 kWh, so the best month makes 3.1 times the worst. November to March brings in 53% of the year's output in Madison County.

MonthWind at 30 mOutputWorth
January6.28 m/s1,853 kWh$356
February6.25 m/s1,654 kWh$318
March6.36 m/s1,903 kWh$366
April6.54 m/s1,948 kWh$375
May5.54 m/s1,389 kWh$267
June4.80 m/s919 kWh$177
July4.17 m/s633 kWh$122
August4.20 m/s646 kWh$124
September4.71 m/s873 kWh$168
October5.78 m/s1,537 kWh$296
November6.21 m/s1,750 kWh$337
December6.10 m/s1,736 kWh$334

What a taller tower would buy

Measured at 10 m the wind in Madison County averages 4.25 m/s; at 50 m it is 6.32 m/s. That gives a shear exponent of 0.247, typical of ordinary open country. Going from 20 m to 50 m takes output from 12,805 to 22,077 kWh a year, 72% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m5.04 m/s12,805 kWh41 years
30 m5.57 m/s16,550 kWh31 years
40 m5.98 m/s19,564 kWh27 years
50 m6.32 m/s22,077 kWh24 years

Counties around Madison County

3 of the 6 closest counties are windier at turbine height; the windiest, Macoupin County, averages 5.84 m/s.

Sun versus wind in Madison County

Madison County gets 4.18 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,221 kWh a year; one kW of the turbine above makes 1,654. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.4 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.