Wind turbine payback in Ogle County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Ogle County, IL averages 5.97 m/s (13.4 mph). A 10 kW turbine there would make about 19,482 kWh a year, worth $3,746 at IL's 19.23¢/kWh. Against an installed cost of about $100,000, that is a payback of 27 years, and the turbine is built to last about 20.

What to do in Ogle County

A home turbine is not worth buying for savings in Ogle County unless your spot is far windier than the county average, 6.8 m/s at the hub against 5.97 m/s here. Per kW, solar panels would make about 1,145 kWh a year here against the turbine's 1,948, so get a solar quote first.

What would have to change

Against the rest of IL

Ogle County is the 891st windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in IL is Cook County at 6.73 m/s, payback 21 years.

Month by month in Ogle County

April is the strongest month here, at 6.90 m/s and about 2,162 kWh. August is the weakest, 4.57 m/s and 832 kWh, so the best month makes 2.6 times the worst. November to March brings in 49% of the year's output in Ogle County.

MonthWind at 30 mOutputWorth
January6.52 m/s1,998 kWh$384
February6.56 m/s1,829 kWh$352
March6.56 m/s2,025 kWh$389
April6.90 m/s2,162 kWh$416
May6.10 m/s1,735 kWh$334
June5.30 m/s1,198 kWh$230
July4.65 m/s869 kWh$167
August4.57 m/s832 kWh$160
September5.45 m/s1,287 kWh$247
October6.27 m/s1,841 kWh$354
November6.54 m/s1,949 kWh$375
December6.31 m/s1,869 kWh$359

What a taller tower would buy

Measured at 10 m the wind in Ogle County averages 4.65 m/s; at 50 m it is 6.71 m/s. That gives a shear exponent of 0.228, typical of ordinary open country. Going from 20 m to 50 m takes output from 15,641 to 24,947 kWh a year, 59% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m5.44 m/s15,641 kWh33 years
30 m5.97 m/s19,499 kWh27 years
40 m6.38 m/s22,500 kWh23 years
50 m6.71 m/s24,947 kWh21 years

Counties around Ogle County

5 of the 6 closest counties are windier at turbine height; the windiest, Boone County, averages 6.05 m/s.

Sun versus wind in Ogle County

Ogle County gets 3.92 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,145 kWh a year; one kW of the turbine above makes 1,948. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.7 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.