Wind Turbine Payback in Salem County, NJ

Wind turbine payback in Salem County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Salem County, NJ averages 5.23 m/s (11.7 mph). A 10 kW turbine there would make about 14,116 kWh a year, worth $3,401 at NJ's 24.09¢/kWh. Against an installed cost of about $100,000, that is a payback of 29 years, and the turbine is built to last about 20.

What to do in Salem County

A home turbine is not worth buying for savings in Salem County unless your spot is far windier than the county average, 6.1 m/s at the hub against 5.23 m/s here. Per kW, solar panels would make about 1,188 kWh a year here against the turbine's 1,412, so get a solar quote first.

What would have to change

Against the rest of NJ

Salem County is the 1,360th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in NJ is Cape May County at 6.6 m/s, payback 17 years.

Month by month in Salem County

March is the strongest month here, at 6.07 m/s and about 1,719 kWh. August is the weakest, 4.00 m/s and 557 kWh, so the best month makes 3.1 times the worst. November to March brings in 55% of the year's output in Salem County.

MonthWind at 30 mOutputWorth
January5.99 m/s1,669 kWh$402
February6.13 m/s1,583 kWh$381
March6.07 m/s1,719 kWh$414
April5.88 m/s1,546 kWh$372
May4.93 m/s1,024 kWh$247
June4.51 m/s771 kWh$186
July4.08 m/s595 kWh$143
August4.00 m/s557 kWh$134
September4.52 m/s779 kWh$188
October5.32 m/s1,256 kWh$303
November5.62 m/s1,392 kWh$335
December5.78 m/s1,537 kWh$370

What a taller tower would buy

Measured at 10 m the wind in Salem County averages 3.97 m/s; at 50 m it is 5.94 m/s. That gives a shear exponent of 0.250, typical of ordinary open country. Going from 20 m to 50 m takes output from 10,723 to 19,260 kWh a year, 80% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m4.72 m/s10,723 kWh39 years
30 m5.23 m/s14,101 kWh29 years
40 m5.62 m/s16,891 kWh25 years
50 m5.94 m/s19,260 kWh22 years

Counties around Salem County

2 of the 6 closest counties are windier at turbine height; the windiest, Gloucester County, averages 5.8 m/s.

Sun versus wind in Salem County

Salem County gets 4.07 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,188 kWh a year; one kW of the turbine above makes 1,412. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.2 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.