Wind Turbine Payback in Carroll County, NH

Wind turbine payback in Carroll County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Carroll County, NH averages 3.51 m/s (7.9 mph). A 10 kW turbine there would make about 4,368 kWh a year, worth $1,176 at NH's 26.91¢/kWh. Against an installed cost of about $100,000, that is a payback of 85 years, and the turbine is built to last about 20.

What to do in Carroll County

A home turbine is not worth buying for savings in Carroll County unless your spot is far windier than the county average, 5.8 m/s at the hub against 3.51 m/s here. Per kW, solar panels would make about 1,083 kWh a year here against the turbine's 437, so get a solar quote first.

What would have to change

Against the rest of NH

Carroll County is the 2,496th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in NH is Cheshire County at 3.64 m/s, payback 76 years.

Month by month in Carroll County

March is the strongest month here, at 4.24 m/s and about 667 kWh. August is the weakest, 2.77 m/s and 166 kWh, so the best month makes 4.0 times the worst. November to March brings in 60% of the year's output in Carroll County.

MonthWind at 30 mOutputWorth
January4.15 m/s626 kWh$168
February4.37 m/s658 kWh$177
March4.24 m/s667 kWh$179
April3.89 m/s497 kWh$134
May3.28 m/s299 kWh$80
June2.96 m/s204 kWh$55
July2.78 m/s170 kWh$46
August2.77 m/s166 kWh$45
September2.97 m/s206 kWh$55
October3.40 m/s334 kWh$90
November3.58 m/s381 kWh$103
December3.85 m/s498 kWh$134

What a taller tower would buy

Measured at 10 m the wind in Carroll County averages 2.24 m/s; at 50 m it is 4.33 m/s. That gives a shear exponent of 0.410, typical of rough, sheltered ground: trees or buildings slow the low wind a lot. Going from 20 m to 50 m takes output from 2,524 to 8,346 kWh a year, 231% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m2.97 m/s2,524 kWhover 100 years
30 m3.51 m/s4,376 kWh85 years
40 m3.95 m/s6,336 kWh59 years
50 m4.33 m/s8,346 kWh45 years

Counties around Carroll County

4 of the 6 closest counties are windier at turbine height; the windiest, York County, averages 3.93 m/s.

Sun versus wind in Carroll County

Carroll County gets 3.71 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,083 kWh a year; one kW of the turbine above makes 437. Kilowatt for kilowatt, panels make 2.5 times as much here as the turbine. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.