TurbinePayback

Wind Turbine Payback in Lake County, SD

Wind turbine payback in Lake County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Lake County, SD averages 6.61 m/s (14.8 mph). A 10 kW turbine there would make about 24,216 kWh a year, worth $3,531 at SD's 14.58¢/kWh. Against an installed cost of about $100,000, that is a payback of 28 years, and the turbine is built to last about 20.

What to do in Lake County

A home turbine is not worth buying for savings in Lake County unless your spot is far windier than the county average, 8.1 m/s at the hub against 6.61 m/s here. Per kW, solar panels would make about 1,191 kWh a year here against the turbine's 2,422, so get a solar quote first.

What would have to change

Against the rest of SD

Lake County is the 107th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in SD is Todd County at 6.77 m/s, payback 27 years.

Month by month in Lake County

April is the strongest month here, at 7.41 m/s and about 2,458 kWh. August is the weakest, 5.63 m/s and 1,440 kWh, so the best month makes 1.7 times the worst. November to March brings in 43% of the year's output in Lake County.

MonthWind at 30 mOutputWorth
January6.62 m/s2,066 kWh$301
February6.71 m/s1,911 kWh$279
March6.99 m/s2,293 kWh$334
April7.41 m/s2,458 kWh$358
May6.92 m/s2,249 kWh$328
June6.26 m/s1,781 kWh$260
July5.63 m/s1,440 kWh$210
August5.63 m/s1,440 kWh$210
September6.72 m/s2,059 kWh$300
October7.04 m/s2,320 kWh$338
November6.82 m/s2,118 kWh$309
December6.56 m/s2,027 kWh$296

What a taller tower would buy

Measured at 10 m the wind in Lake County averages 5.27 m/s; at 50 m it is 7.34 m/s. That gives a shear exponent of 0.206, typical of ordinary open country. Going from 20 m to 50 m takes output from 20,278 to 29,437 kWh a year, 45% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m6.08 m/s20,278 kWh34 years
30 m6.61 m/s24,193 kWh28 years
40 m7.01 m/s27,116 kWh25 years
50 m7.34 m/s29,437 kWh23 years

Counties around Lake County

1 of the 6 closest counties is windier at turbine height; the windiest, Brookings County, averages 6.69 m/s.

Sun versus wind in Lake County

Lake County gets 4.08 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,191 kWh a year; one kW of the turbine above makes 2,422. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 2.0 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.