Wind Turbine Payback in Navajo County, AZ

Wind turbine payback in Navajo County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Navajo County, AZ averages 4.66 m/s (10.4 mph). A 10 kW turbine there would make about 10,320 kWh a year, worth $1,585 at AZ's 15.36¢/kWh. Against an installed cost of about $100,000, that is a payback of 63 years, and the turbine is built to last about 20.

What to do in Navajo County

A home turbine is not worth buying for savings in Navajo County unless your spot is far windier than the county average, 7.8 m/s at the hub against 4.66 m/s here. Per kW, solar panels would make about 1,647 kWh a year here against the turbine's 1,032, so get a solar quote first.

What would have to change

Against the rest of AZ

Navajo County is the 1,645th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in AZ is Apache County at 5.25 m/s, payback 46 years.

Month by month in Navajo County

April is the strongest month here, at 5.77 m/s and about 1,480 kWh. August is the weakest, 3.54 m/s and 381 kWh, so the best month makes 3.9 times the worst. November to March brings in 42% of the year's output in Navajo County.

MonthWind at 30 mOutputWorth
January4.44 m/s761 kWh$117
February4.91 m/s914 kWh$140
March5.20 m/s1,182 kWh$182
April5.77 m/s1,480 kWh$227
May5.25 m/s1,208 kWh$186
June5.03 m/s1,048 kWh$161
July3.93 m/s529 kWh$81
August3.54 m/s381 kWh$59
September4.18 m/s617 kWh$95
October4.68 m/s885 kWh$136
November4.68 m/s857 kWh$132
December4.39 m/s739 kWh$114

What a taller tower would buy

Measured at 10 m the wind in Navajo County averages 3.62 m/s; at 50 m it is 5.24 m/s. That gives a shear exponent of 0.230, typical of ordinary open country. Going from 20 m to 50 m takes output from 7,866 to 14,186 kWh a year, 80% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m4.24 m/s7,866 kWh83 years
30 m4.66 m/s10,314 kWh63 years
40 m4.98 m/s12,385 kWh53 years
50 m5.24 m/s14,186 kWh46 years

Counties around Navajo County

3 of the 6 closest counties are windier at turbine height; the windiest, Cibola County, averages 5.8 m/s.

Sun versus wind in Navajo County

Navajo County gets 5.64 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,647 kWh a year; one kW of the turbine above makes 1,032. Kilowatt for kilowatt, panels make 1.6 times as much here as the turbine. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.