TurbinePayback

Wind Turbine Payback in Stone County, MS

Wind turbine payback in Stone County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Stone County, MS averages 2.93 m/s (6.6 mph). A 10 kW turbine there would make about 2,398 kWh a year, worth $361 at MS's 15.06¢/kWh. Against an installed cost of about $100,000, that is a payback of over 100 years, and the turbine is built to last about 20.

What to do in Stone County

A home turbine is not worth buying for savings in Stone County unless your spot is far windier than the county average, 7.9 m/s at the hub against 2.93 m/s here. Per kW, solar panels would make about 1,384 kWh a year here against the turbine's 240, so get a solar quote first.

What would have to change

Against the rest of MS

Stone County is the 3,098th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in MS is DeSoto County at 5.13 m/s, payback 50 years.

Month by month in Stone County

March is the strongest month here, at 3.33 m/s and about 313 kWh. July is the weakest, 2.28 m/s and 79 kWh, so the best month makes 4.0 times the worst. November to March brings in 55% of the year's output in Stone County.

MonthWind at 30 mOutputWorth
January3.21 m/s279 kWh$42
February3.30 m/s274 kWh$41
March3.33 m/s313 kWh$47
April3.30 m/s294 kWh$44
May2.90 m/s196 kWh$30
June2.48 m/s107 kWh$16
July2.28 m/s79 kWh$12
August2.35 m/s91 kWh$14
September2.70 m/s147 kWh$22
October2.97 m/s215 kWh$32
November3.17 m/s257 kWh$39
December3.18 m/s270 kWh$41

What a taller tower would buy

Measured at 10 m the wind in Stone County averages 1.69 m/s; at 50 m it is 3.78 m/s. That gives a shear exponent of 0.500, typical of rough, sheltered ground: trees or buildings slow the low wind a lot. Going from 20 m to 50 m takes output from 1,136 to 5,523 kWh a year, 386% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m2.39 m/s1,136 kWhover 100 years
30 m2.93 m/s2,393 kWhover 100 years
40 m3.38 m/s3,871 kWhover 100 years
50 m3.78 m/s5,523 kWhover 100 years

Counties around Stone County

4 of the 6 closest counties are windier at turbine height; the windiest, Perry County, averages 3.41 m/s.

Sun versus wind in Stone County

Stone County gets 4.74 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,384 kWh a year; one kW of the turbine above makes 240. Kilowatt for kilowatt, panels make 5.8 times as much here as the turbine. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.