Wind Turbine Payback in Woodward County, OK

Wind turbine payback in Woodward County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Woodward County, OK averages 6.69 m/s (15 mph). A 10 kW turbine there would make about 24,801 kWh a year, worth $3,425 at OK's 13.81¢/kWh. Against an installed cost of about $100,000, that is a payback of 29 years, and the turbine is built to last about 20.

What to do in Woodward County

A home turbine is not worth buying for savings in Woodward County unless your spot is far windier than the county average, 8.4 m/s at the hub against 6.69 m/s here. Per kW, solar panels would make about 1,442 kWh a year here against the turbine's 2,480, so get a solar quote first.

What would have to change

Against the rest of OK

Woodward County is the 65th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in OK is Cimarron County at 6.82 m/s, payback 28 years.

Month by month in Woodward County

April is the strongest month here, at 7.60 m/s and about 2,566 kWh. August is the weakest, 5.91 m/s and 1,619 kWh, so the best month makes 1.6 times the worst. November to March brings in 41% of the year's output in Woodward County.

MonthWind at 30 mOutputWorth
January6.49 m/s1,980 kWh$273
February6.53 m/s1,814 kWh$251
March7.11 m/s2,362 kWh$326
April7.60 m/s2,566 kWh$354
May6.94 m/s2,258 kWh$312
June6.98 m/s2,212 kWh$305
July6.09 m/s1,732 kWh$239
August5.91 m/s1,619 kWh$224
September6.51 m/s1,933 kWh$267
October6.80 m/s2,176 kWh$301
November6.86 m/s2,138 kWh$295
December6.50 m/s1,986 kWh$274

What a taller tower would buy

Measured at 10 m the wind in Woodward County averages 5.3 m/s; at 50 m it is 7.46 m/s. That gives a shear exponent of 0.212, typical of ordinary open country. Going from 20 m to 50 m takes output from 20,764 to 30,263 kWh a year, 46% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m6.14 m/s20,764 kWh35 years
30 m6.69 m/s24,833 kWh29 years
40 m7.12 m/s27,863 kWh26 years
50 m7.46 m/s30,263 kWh24 years

Counties around Woodward County

1 of the 6 closest counties is windier at turbine height; the windiest, Ellis County, averages 6.76 m/s.

Sun versus wind in Woodward County

Woodward County gets 4.94 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,442 kWh a year; one kW of the turbine above makes 2,480. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.7 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.