Wind Turbine Payback in Chouteau County, MT

Wind turbine payback in Chouteau County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Chouteau County, MT averages 6.09 m/s (13.6 mph). A 10 kW turbine there would make about 20,371 kWh a year, worth $2,878 at MT's 14.13¢/kWh. Against an installed cost of about $100,000, that is a payback of 35 years, and the turbine is built to last about 20.

What to do in Chouteau County

A home turbine is not worth buying for savings in Chouteau County unless your spot is far windier than the county average, 8.2 m/s at the hub against 6.09 m/s here. Per kW, solar panels would make about 1,165 kWh a year here against the turbine's 2,037, so get a solar quote first.

What would have to change

Against the rest of MT

Chouteau County is the 701st windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in MT is Fallon County at 6.64 m/s, payback 29 years.

Month by month in Chouteau County

January is the strongest month here, at 7.07 m/s and about 2,341 kWh. August is the weakest, 4.88 m/s and 999 kWh, so the best month makes 2.3 times the worst. November to March brings in 51% of the year's output in Chouteau County.

MonthWind at 30 mOutputWorth
January7.07 m/s2,341 kWh$331
February6.32 m/s1,691 kWh$239
March6.48 m/s1,973 kWh$279
April6.09 m/s1,677 kWh$237
May5.75 m/s1,515 kWh$214
June5.60 m/s1,375 kWh$194
July5.11 m/s1,126 kWh$159
August4.88 m/s999 kWh$141
September5.44 m/s1,285 kWh$182
October6.44 m/s1,951 kWh$276
November7.08 m/s2,270 kWh$321
December6.85 m/s2,205 kWh$312

What a taller tower would buy

Measured at 10 m the wind in Chouteau County averages 4.74 m/s; at 50 m it is 6.85 m/s. That gives a shear exponent of 0.229, typical of ordinary open country. Going from 20 m to 50 m takes output from 16,424 to 25,964 kWh a year, 58% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m5.55 m/s16,424 kWh43 years
30 m6.09 m/s20,399 kWh35 years
40 m6.51 m/s23,472 kWh30 years
50 m6.85 m/s25,964 kWh27 years

Counties around Chouteau County

4 of the 6 closest counties are windier at turbine height; the windiest, Blaine County, averages 6.31 m/s.

Sun versus wind in Chouteau County

Chouteau County gets 3.99 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,165 kWh a year; one kW of the turbine above makes 2,037. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.7 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.