TurbinePayback

Wind Turbine Payback in Graham County, AZ

Wind turbine payback in Graham County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Graham County, AZ averages 4.09 m/s (9.1 mph). A 10 kW turbine there would make about 7,038 kWh a year, worth $1,081 at AZ's 15.36¢/kWh. Against an installed cost of about $100,000, that is a payback of 93 years, and the turbine is built to last about 20.

What to do in Graham County

A home turbine is not worth buying for savings in Graham County unless your spot is far windier than the county average, 7.8 m/s at the hub against 4.09 m/s here. Per kW, solar panels would make about 1,699 kWh a year here against the turbine's 704, so get a solar quote first.

What would have to change

Against the rest of AZ

Graham County is the 2,005th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in AZ is Apache County at 5.25 m/s, payback 46 years.

Month by month in Graham County

April is the strongest month here, at 4.65 m/s and about 844 kWh. August is the weakest, 3.36 m/s and 321 kWh, so the best month makes 2.6 times the worst. November to March brings in 43% of the year's output in Graham County.

MonthWind at 30 mOutputWorth
January4.04 m/s576 kWh$88
February4.15 m/s563 kWh$86
March4.35 m/s716 kWh$110
April4.65 m/s844 kWh$130
May4.44 m/s761 kWh$117
June4.31 m/s676 kWh$104
July3.71 m/s441 kWh$68
August3.36 m/s321 kWh$49
September3.86 m/s484 kWh$74
October4.00 m/s560 kWh$86
November4.27 m/s660 kWh$101
December4.06 m/s583 kWh$90

What a taller tower would buy

Measured at 10 m the wind in Graham County averages 3.26 m/s; at 50 m it is 4.55 m/s. That gives a shear exponent of 0.207, typical of ordinary open country. Going from 20 m to 50 m takes output from 5,449 to 9,641 kWh a year, 77% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m3.76 m/s5,449 kWhover 100 years
30 m4.09 m/s7,056 kWh92 years
40 m4.34 m/s8,429 kWh77 years
50 m4.55 m/s9,641 kWh68 years

Counties around Graham County

5 of the 6 closest counties are windier at turbine height; the windiest, Grant County, averages 5.52 m/s.

Sun versus wind in Graham County

Graham County gets 5.82 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,699 kWh a year; one kW of the turbine above makes 704. Kilowatt for kilowatt, panels make 2.4 times as much here as the turbine. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.