Wind Turbine Payback in Meagher County, MT

Wind turbine payback in Meagher County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Meagher County, MT averages 4.63 m/s (10.4 mph). A 10 kW turbine there would make about 10,132 kWh a year, worth $1,432 at MT's 14.13¢/kWh. Against an installed cost of about $100,000, that is a payback of 70 years, and the turbine is built to last about 20.

What to do in Meagher County

A home turbine is not worth buying for savings in Meagher County unless your spot is far windier than the county average, 8.2 m/s at the hub against 4.63 m/s here. Per kW, solar panels would make about 1,183 kWh a year here against the turbine's 1,013, so get a solar quote first.

What would have to change

Against the rest of MT

Meagher County is the 1,671st windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in MT is Fallon County at 6.64 m/s, payback 29 years.

Month by month in Meagher County

January is the strongest month here, at 5.61 m/s and about 1,427 kWh. July is the weakest, 3.60 m/s and 401 kWh, so the best month makes 3.6 times the worst. November to March brings in 59% of the year's output in Meagher County.

MonthWind at 30 mOutputWorth
January5.61 m/s1,427 kWh$202
February5.10 m/s1,013 kWh$143
March5.06 m/s1,102 kWh$156
April4.61 m/s822 kWh$116
May4.15 m/s627 kWh$89
June4.01 m/s544 kWh$77
July3.60 m/s401 kWh$57
August3.61 m/s404 kWh$57
September4.05 m/s562 kWh$79
October4.87 m/s989 kWh$140
November5.43 m/s1,279 kWh$181
December5.44 m/s1,327 kWh$188

What a taller tower would buy

Measured at 10 m the wind in Meagher County averages 3.33 m/s; at 50 m it is 5.39 m/s. That gives a shear exponent of 0.299, typical of ordinary open country. Going from 20 m to 50 m takes output from 7,081 to 15,247 kWh a year, 115% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m4.1 m/s7,081 kWh100 years
30 m4.63 m/s10,111 kWh70 years
40 m5.04 m/s12,820 kWh55 years
50 m5.39 m/s15,247 kWh46 years

Counties around Meagher County

4 of the 6 closest counties are windier at turbine height; the windiest, Judith Basin County, averages 5.97 m/s.

Sun versus wind in Meagher County

Meagher County gets 4.05 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,183 kWh a year; one kW of the turbine above makes 1,013. Kilowatt for kilowatt, panels make 1.2 times as much here as the turbine. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.