Wind Turbine Payback in Niobrara County, WY

Wind turbine payback in Niobrara County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Niobrara County, WY averages 6.56 m/s (14.7 mph). A 10 kW turbine there would make about 23,849 kWh a year, worth $3,341 at WY's 14.01¢/kWh. Against an installed cost of about $100,000, that is a payback of 30 years, and the turbine is built to last about 20.

What to do in Niobrara County

A home turbine is not worth buying for savings in Niobrara County unless your spot is far windier than the county average, 8.3 m/s at the hub against 6.56 m/s here. Per kW, solar panels would make about 1,296 kWh a year here against the turbine's 2,385, so get a solar quote first.

What would have to change

Against the rest of WY

Niobrara County is the 139th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in WY is Albany County at 7.32 m/s, payback 24 years.

Month by month in Niobrara County

January is the strongest month here, at 7.75 m/s and about 2,733 kWh. July is the weakest, 5.35 m/s and 1,272 kWh, so the best month makes 2.1 times the worst. November to March brings in 51% of the year's output in Niobrara County.

MonthWind at 30 mOutputWorth
January7.75 m/s2,733 kWh$383
February7.18 m/s2,173 kWh$304
March6.89 m/s2,232 kWh$313
April6.62 m/s1,994 kWh$279
May6.11 m/s1,745 kWh$244
June5.77 m/s1,482 kWh$208
July5.35 m/s1,272 kWh$178
August5.50 m/s1,365 kWh$191
September5.93 m/s1,574 kWh$221
October6.69 m/s2,105 kWh$295
November7.28 m/s2,385 kWh$334
December7.66 m/s2,688 kWh$377

What a taller tower would buy

Measured at 10 m the wind in Niobrara County averages 5.19 m/s; at 50 m it is 7.32 m/s. That gives a shear exponent of 0.214, typical of ordinary open country. Going from 20 m to 50 m takes output from 19,827 to 29,299 kWh a year, 48% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m6.02 m/s19,827 kWh36 years
30 m6.56 m/s23,863 kWh30 years
40 m6.98 m/s26,890 kWh27 years
50 m7.32 m/s29,299 kWh24 years

Counties around Niobrara County

1 of the 6 closest counties is windier at turbine height; the windiest, Converse County, averages 6.97 m/s.

Sun versus wind in Niobrara County

Niobrara County gets 4.44 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,296 kWh a year; one kW of the turbine above makes 2,385. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.8 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.