TurbinePayback

Wind Turbine Payback in Outagamie County, WI

Wind turbine payback in Outagamie County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Outagamie County, WI averages 6.01 m/s (13.4 mph). A 10 kW turbine there would make about 19,778 kWh a year, worth $3,768 at WI's 19.05¢/kWh. Against an installed cost of about $100,000, that is a payback of 27 years, and the turbine is built to last about 20.

What to do in Outagamie County

A home turbine is not worth buying for savings in Outagamie County unless your spot is far windier than the county average, 6.9 m/s at the hub against 6.01 m/s here. Per kW, solar panels would make about 1,113 kWh a year here against the turbine's 1,978, so get a solar quote first.

What would have to change

Against the rest of WI

Outagamie County is the 826th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in WI is Manitowoc County at 7.32 m/s, payback 18 years.

Month by month in Outagamie County

January is the strongest month here, at 6.56 m/s and about 2,023 kWh. August is the weakest, 5.01 m/s and 1,072 kWh, so the best month makes 1.9 times the worst. November to March brings in 48% of the year's output in Outagamie County.

MonthWind at 30 mOutputWorth
January6.56 m/s2,023 kWh$385
February6.72 m/s1,922 kWh$366
March6.39 m/s1,916 kWh$365
April6.64 m/s2,006 kWh$382
May5.93 m/s1,630 kWh$311
June5.35 m/s1,231 kWh$235
July5.02 m/s1,077 kWh$205
August5.01 m/s1,072 kWh$204
September5.70 m/s1,437 kWh$274
October6.33 m/s1,883 kWh$359
November6.30 m/s1,800 kWh$343
December6.30 m/s1,860 kWh$354

What a taller tower would buy

Measured at 10 m the wind in Outagamie County averages 4.7 m/s; at 50 m it is 6.74 m/s. That gives a shear exponent of 0.224, typical of ordinary open country. Going from 20 m to 50 m takes output from 15,960 to 25,166 kWh a year, 58% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m5.49 m/s15,960 kWh33 years
30 m6.01 m/s19,788 kWh27 years
40 m6.41 m/s22,753 kWh23 years
50 m6.74 m/s25,166 kWh21 years

Counties around Outagamie County

3 of the 6 closest counties are windier at turbine height; the windiest, Calumet County, averages 6.53 m/s.

Sun versus wind in Outagamie County

Outagamie County gets 3.81 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,113 kWh a year; one kW of the turbine above makes 1,978. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.8 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.