Wind Turbine Payback in Pend Oreille County, WA

Wind turbine payback in Pend Oreille County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Pend Oreille County, WA averages 2.48 m/s (5.5 mph). A 10 kW turbine there would make about 1,310 kWh a year, worth $189 at WA's 14.42¢/kWh. Against an installed cost of about $100,000, that is a payback of over 100 years, and the turbine is built to last about 20.

What to do in Pend Oreille County

A home turbine is not worth buying for savings in Pend Oreille County unless your spot is far windier than the county average, 8.1 m/s at the hub against 2.48 m/s here. Per kW, solar panels would make about 1,063 kWh a year here against the turbine's 131, so get a solar quote first.

What would have to change

Against the rest of WA

Pend Oreille County is the 3,140th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in WA is Columbia County at 5.18 m/s, payback 50 years.

Month by month in Pend Oreille County

March is the strongest month here, at 2.68 m/s and about 148 kWh. January is the weakest, 2.30 m/s and 83 kWh, so the best month makes 1.8 times the worst. November to March brings in 39% of the year's output in Pend Oreille County.

MonthWind at 30 mOutputWorth
January2.30 m/s83 kWh$12
February2.40 m/s89 kWh$13
March2.68 m/s148 kWh$21
April2.67 m/s141 kWh$20
May2.48 m/s111 kWh$16
June2.44 m/s101 kWh$15
July2.50 m/s115 kWh$17
August2.47 m/s109 kWh$16
September2.52 m/s114 kWh$16
October2.50 m/s115 kWh$17
November2.45 m/s103 kWh$15
December2.36 m/s92 kWh$13

What a taller tower would buy

Measured at 10 m the wind in Pend Oreille County averages 1.63 m/s; at 50 m it is 3.01 m/s. That gives a shear exponent of 0.381, typical of rough, sheltered ground: trees or buildings slow the low wind a lot. Going from 20 m to 50 m takes output from 692 to 2,631 kWh a year, 280% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m2.12 m/s692 kWhover 100 years
30 m2.48 m/s1,305 kWhover 100 years
40 m2.76 m/s1,957 kWhover 100 years
50 m3.01 m/s2,631 kWhover 100 years

Counties around Pend Oreille County

5 of the 6 closest counties are windier at turbine height; the windiest, Spokane County, averages 4.42 m/s.

Sun versus wind in Pend Oreille County

Pend Oreille County gets 3.64 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,063 kWh a year; one kW of the turbine above makes 131. Kilowatt for kilowatt, panels make 8.1 times as much here as the turbine. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.