TurbinePayback

Wind Turbine Payback in Powder River County, MT

Wind turbine payback in Powder River County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Powder River County, MT averages 6.12 m/s (13.7 mph). A 10 kW turbine there would make about 20,594 kWh a year, worth $2,910 at MT's 14.13¢/kWh. Against an installed cost of about $100,000, that is a payback of 34 years, and the turbine is built to last about 20.

What to do in Powder River County

A home turbine is not worth buying for savings in Powder River County unless your spot is far windier than the county average, 8.2 m/s at the hub against 6.12 m/s here. Per kW, solar panels would make about 1,235 kWh a year here against the turbine's 2,059, so get a solar quote first.

What would have to change

Against the rest of MT

Powder River County is the 664th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in MT is Fallon County at 6.64 m/s, payback 29 years.

Month by month in Powder River County

January is the strongest month here, at 6.85 m/s and about 2,205 kWh. July is the weakest, 5.28 m/s and 1,231 kWh, so the best month makes 1.8 times the worst. November to March brings in 47% of the year's output in Powder River County.

MonthWind at 30 mOutputWorth
January6.85 m/s2,205 kWh$312
February6.28 m/s1,669 kWh$236
March6.35 m/s1,893 kWh$267
April6.20 m/s1,739 kWh$246
May6.03 m/s1,690 kWh$239
June5.66 m/s1,414 kWh$200
July5.28 m/s1,231 kWh$174
August5.36 m/s1,280 kWh$181
September5.80 m/s1,500 kWh$212
October6.44 m/s1,949 kWh$275
November6.51 m/s1,930 kWh$273
December6.60 m/s2,050 kWh$290

What a taller tower would buy

Measured at 10 m the wind in Powder River County averages 4.81 m/s; at 50 m it is 6.84 m/s. That gives a shear exponent of 0.219, typical of ordinary open country. Going from 20 m to 50 m takes output from 16,735 to 25,892 kWh a year, 55% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m5.6 m/s16,735 kWh42 years
30 m6.12 m/s20,565 kWh34 years
40 m6.51 m/s23,509 kWh30 years
50 m6.84 m/s25,892 kWh27 years

Counties around Powder River County

2 of the 6 closest counties are windier at turbine height; the windiest, Fallon County, averages 6.64 m/s.

Sun versus wind in Powder River County

Powder River County gets 4.23 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,235 kWh a year; one kW of the turbine above makes 2,059. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 1.7 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.