TurbinePayback

Wind Turbine Payback in Todd County, MN

Wind turbine payback in Todd County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Todd County, MN averages 6.45 m/s (14.4 mph). A 10 kW turbine there would make about 23,038 kWh a year, worth $3,787 at MN's 16.44¢/kWh. Against an installed cost of about $100,000, that is a payback of 26 years, and the turbine is built to last about 20.

What to do in Todd County

A home turbine is not worth buying for savings in Todd County unless your spot is far windier than the county average, 7.5 m/s at the hub against 6.45 m/s here. Per kW, solar panels would make about 1,101 kWh a year here against the turbine's 2,304, so get a solar quote first.

What would have to change

Against the rest of MN

Todd County is the 257th windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in MN is Lincoln County at 6.68 m/s, payback 25 years.

Month by month in Todd County

April is the strongest month here, at 7.04 m/s and about 2,247 kWh. July is the weakest, 5.47 m/s and 1,342 kWh, so the best month makes 1.7 times the worst. November to March brings in 44% of the year's output in Todd County.

MonthWind at 30 mOutputWorth
January6.69 m/s2,106 kWh$346
February6.75 m/s1,938 kWh$319
March6.70 m/s2,112 kWh$347
April7.04 m/s2,247 kWh$369
May6.66 m/s2,090 kWh$344
June6.03 m/s1,640 kWh$270
July5.47 m/s1,342 kWh$221
August5.58 m/s1,414 kWh$232
September6.52 m/s1,935 kWh$318
October6.84 m/s2,201 kWh$362
November6.66 m/s2,022 kWh$332
December6.45 m/s1,955 kWh$321

What a taller tower would buy

Measured at 10 m the wind in Todd County averages 5.13 m/s; at 50 m it is 7.17 m/s. That gives a shear exponent of 0.208, typical of ordinary open country. Going from 20 m to 50 m takes output from 19,155 to 28,250 kWh a year, 47% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m5.93 m/s19,155 kWh32 years
30 m6.45 m/s23,018 kWh26 years
40 m6.84 m/s25,927 kWh24 years
50 m7.17 m/s28,250 kWh22 years

Counties around Todd County

2 of the 6 closest counties are windier at turbine height; the windiest, Otter Tail County, averages 6.59 m/s.

Sun versus wind in Todd County

Todd County gets 3.77 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,101 kWh a year; one kW of the turbine above makes 2,304. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 2.1 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.