Wind Turbine Payback in Bowman County, ND

Wind turbine payback in Bowman County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Bowman County, ND averages 6.79 m/s (15.2 mph). A 10 kW turbine there would make about 25,529 kWh a year, worth $3,181 at ND's 12.46¢/kWh. Against an installed cost of about $100,000, that is a payback of 31 years, and the turbine is built to last about 20.

What to do in Bowman County

A home turbine is not worth buying for savings in Bowman County unless your spot is far windier than the county average, 9.1 m/s at the hub against 6.79 m/s here. Per kW, solar panels would make about 1,194 kWh a year here against the turbine's 2,553, so get a solar quote first.

What would have to change

Against the rest of ND

Bowman County is the 33rd windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. It is the windiest county in ND.

Month by month in Bowman County

January is the strongest month here, at 7.60 m/s and about 2,650 kWh. July is the weakest, 5.79 m/s and 1,544 kWh, so the best month makes 1.7 times the worst. November to March brings in 47% of the year's output in Bowman County.

MonthWind at 30 mOutputWorth
January7.60 m/s2,650 kWh$330
February6.88 m/s2,006 kWh$250
March7.03 m/s2,315 kWh$288
April6.89 m/s2,160 kWh$269
May6.68 m/s2,099 kWh$262
June6.26 m/s1,780 kWh$222
July5.79 m/s1,544 kWh$192
August5.93 m/s1,629 kWh$203
September6.49 m/s1,917 kWh$239
October7.19 m/s2,413 kWh$301
November7.30 m/s2,397 kWh$299
December7.36 m/s2,514 kWh$313

What a taller tower would buy

Measured at 10 m the wind in Bowman County averages 5.44 m/s; at 50 m it is 7.52 m/s. That gives a shear exponent of 0.201, typical of ordinary open country. Going from 20 m to 50 m takes output from 21,596 to 30,672 kWh a year, 42% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m6.26 m/s21,596 kWh37 years
30 m6.79 m/s25,502 kWh32 years
40 m7.19 m/s28,392 kWh28 years
50 m7.52 m/s30,672 kWh26 years

Counties around Bowman County

None of the 6 closest counties is windier than Bowman County.

Sun versus wind in Bowman County

Bowman County gets 4.09 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,194 kWh a year; one kW of the turbine above makes 2,553. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 2.1 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.