Wind Turbine Payback in Cass County, ND

Wind turbine payback in Cass County

No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Cass County, ND averages 6.35 m/s (14.2 mph). A 10 kW turbine there would make about 22,299 kWh a year, worth $2,778 at ND's 12.46¢/kWh. Against an installed cost of about $100,000, that is a payback of 36 years, and the turbine is built to last about 20.

What to do in Cass County

A home turbine is not worth buying for savings in Cass County unless your spot is far windier than the county average, 9.1 m/s at the hub against 6.35 m/s here. Per kW, solar panels would make about 1,142 kWh a year here against the turbine's 2,230, so get a solar quote first.

What would have to change

Against the rest of ND

Cass County is the 402nd windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in ND is Bowman County at 6.79 m/s, payback 31 years.

Month by month in Cass County

October is the strongest month here, at 6.91 m/s and about 2,243 kWh. July is the weakest, 5.50 m/s and 1,359 kWh, so the best month makes 1.7 times the worst. November to March brings in 42% of the year's output in Cass County.

MonthWind at 30 mOutputWorth
January6.37 m/s1,909 kWh$238
February6.33 m/s1,699 kWh$212
March6.54 m/s2,016 kWh$251
April6.84 m/s2,128 kWh$265
May6.70 m/s2,110 kWh$263
June6.04 m/s1,645 kWh$205
July5.50 m/s1,359 kWh$169
August5.62 m/s1,436 kWh$179
September6.48 m/s1,913 kWh$238
October6.91 m/s2,243 kWh$279
November6.56 m/s1,961 kWh$244
December6.26 m/s1,836 kWh$229

What a taller tower would buy

Measured at 10 m the wind in Cass County averages 5.02 m/s; at 50 m it is 7.08 m/s. That gives a shear exponent of 0.214, typical of ordinary open country. Going from 20 m to 50 m takes output from 18,369 to 27,613 kWh a year, 50% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m5.82 m/s18,369 kWh44 years
30 m6.35 m/s22,276 kWh36 years
40 m6.75 m/s25,238 kWh32 years
50 m7.08 m/s27,613 kWh29 years

Counties around Cass County

4 of the 6 closest counties are windier at turbine height; the windiest, Clay County, averages 6.45 m/s.

Sun versus wind in Cass County

Cass County gets 3.91 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,142 kWh a year; one kW of the turbine above makes 2,230. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 2.0 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.