No. The turbine wears out before it pays for itself.

At 30 m, the height a home turbine tower usually reaches, the wind in Traill County, ND averages 6.29 m/s (14.1 mph). A 10 kW turbine there would make about 21,855 kWh a year, worth $2,723 at ND's 12.46¢/kWh. Against an installed cost of about $100,000, that is a payback of 37 years, and the turbine is built to last about 20.

What to do in Traill County

A home turbine is not worth buying for savings in Traill County unless your spot is far windier than the county average, 9.1 m/s at the hub against 6.29 m/s here. Per kW, solar panels would make about 1,121 kWh a year here against the turbine's 2,186, so get a solar quote first.

What would have to change

Against the rest of ND

Traill County is the 482nd windiest of 3,144 US counties at turbine height; the national middle is 4.79 m/s. The windiest in ND is Bowman County at 6.79 m/s, payback 31 years.

Month by month in Traill County

October is the strongest month here, at 6.79 m/s and about 2,170 kWh. July is the weakest, 5.52 m/s and 1,374 kWh, so the best month makes 1.6 times the worst. November to March brings in 42% of the year's output in Traill County.

MonthWind at 30 mOutputWorth
January6.27 m/s1,845 kWh$230
February6.26 m/s1,662 kWh$207
March6.54 m/s2,014 kWh$251
April6.81 m/s2,111 kWh$263
May6.64 m/s2,076 kWh$259
June6.02 m/s1,632 kWh$203
July5.52 m/s1,374 kWh$171
August5.62 m/s1,434 kWh$179
September6.43 m/s1,884 kWh$235
October6.79 m/s2,170 kWh$270
November6.49 m/s1,917 kWh$239
December6.15 m/s1,766 kWh$220

What a taller tower would buy

Measured at 10 m the wind in Traill County averages 4.98 m/s; at 50 m it is 7.01 m/s. That gives a shear exponent of 0.212, typical of ordinary open country. Going from 20 m to 50 m takes output from 18,023 to 27,114 kWh a year, 50% more, before counting the extra cost of the taller tower. Why tower height decides it explains the shear behind these numbers.

Hub heightAverage windOutputPayback
20 m5.77 m/s18,023 kWh45 years
30 m6.29 m/s21,858 kWh37 years
40 m6.69 m/s24,773 kWh32 years
50 m7.01 m/s27,114 kWh30 years

Counties around Traill County

6 of the 6 closest counties are windier at turbine height; the windiest, Clay County, averages 6.45 m/s.

Sun versus wind in Traill County

Traill County gets 3.84 kWh of sunshine per square metre a day on average. One kW of solar panels here would make roughly 1,121 kWh a year; one kW of the turbine above makes 2,186. This is one of the rare places where a kilowatt of turbine out-produces a kilowatt of panels, by 2.0 times. Panel output assumes an 80% system performance ratio. Wind or solar runs the same comparison for every county.

How this is worked out

Wind is NASA's Power climate record, the 2001-2025 average at 10 m and 50 m for the county's centre, carried to 30 m with this county's own measured wind shear and spread into hours with a Rayleigh distribution. The turbine is a generic 10 kW, 7 m rotor machine with 10% losses. Cost is $10,000 per kW installed with no tax credit, because the federal one ended in 2025. One county-centre number cannot see your hilltop or your tree line, so treat it as the starting point for a site survey, not a substitute. The full method and its weak spots are in how the numbers are made.